India’s energy demand and supply deficit

For the past two decades, India has had to face increasing deficit in power supply, both for meeting its normal energy requirements as well as its peak load demand. The problem is acute during peak hours and summers, and necessitates planned load shedding by many utilities to maintain the grid in a healthy state. The average all-India shortages in 2009-10 were at 10 per cent in terms of normal energy requirement and about 13 per cent in terms of peak load.

Electricity Demand and Supply

FY

Energy

Peak Demand

(MU)

(MW)

Demand Availability Shortage % Demand Met Shortage %
2002-03 545,983 497,890 48,093 8.8 81,492 71,547 9,945 12.2
2003-04 559,264 519,398 39,866 7.1 84,574 75,066 9,508 11.2
2004-05 591,373 548,115 43,258 7.3 87,906 77,652 10,254 11.7
2005-06 631,024 578,511 52,513 8.3 93,214 81,792 11,422 12.3
2006-07 693,057 624,716 68,341 9.9 100,715 86,818 13,897 13.8
2007-08 737,052 664,660 72,392 9.8 108,866 90,793 18,073 16.6
2008-09 777,039 691,038 86,001 11.1 109,809 96,785 13,024 11.9
2009-10 830,594 746,644 83,950 10.1 118,472 102,725 15,747 13.3

Source: CEA

With the shortage at both the normal and the peak levels, Indian power industry does not exhibit much cyclicality. Further, with assured returns, the margins of players and their profitability is almost independent of the economic cycles. Electricity is the most important component of primary energy. India’s electricity consumption has grown at an average rate of 7.3 per cent during the period 2002-07 to about 577.9 TWh. Consumption has increased at a faster rate since 2002-03, reflecting buoyant industrial demand. Industrial consumers are the largest group of electricity consumers, followed by the domestic, agricultural and commercial consumers, in that order. India’s per capita electricity consumption increased from 178 kWh in 1985-86 to 704.4 kWh in 2007-08. Over the period, 2001-08, per capita consumption has increased at an average rate of 4.45 per cent. It is still much lower compared to the international standards.

 

 

Electricity Requirement

The demand for power is expected to increase to 975 billion kWh by 2011-12. However, at an average GDP growth rate of 8 per cent, the overall demand is expected to increase to about 1,097 billion kWh in 2011-12, including the demand from non-utilities.

Projected Requirement of Electricity

Energy Requirement

Peak Demand

Installed Capacity Required

(Billion kWh)

(GW)

(GW)

GDP growth at

8.0%

9.0%

8.0%

9.0%

8.0%

9.0%

2003-04

633

633

89

89

131

131

2006-07

761

774

107

109

153

155

2011-12

1,097

1,167

158

168

220

233

2016-17

1,524

1,687

226

250

306

337

2021-22

2,118

2,438

323

372

425

488

2026-27

2,866

3,423

437

522

575

685

2031-32

3,880

4,806

592

733

778

960

Source: IMaCS Research

The 17th Electric Power Survey (EPS) has forecast a peak demand of 152,746 MW for 2010-11. That means a capacity addition requirement of about 72,000 MW during the Eleventh Plan period. Though the target set for capacity addition during the Eleventh Plan period is 78,700 MW, only 62,000 MW is expected to be added by the end of the period.

Capacity Addition Plan

The following table provides the Eleventh Plan targets for adding generation capacity. In a reversal of the trend witnessed during the 1990s, a substantial contribution is expected from the hydropower sector. Also, the private sector is expected to account for 15 GW of the planned capacity addition of 78.7 GW during this period.

Installed Capacity Addition Plan (MW)

Sector Thermal Hydro Nuclear Grand Total
11thPlan Total 59,693 15,627 3,380 78,700
Central 24,840 8,654 3,380 36,874
State 23,301 3,482 - 26,783
Private 11,552 3,491 - 15,043

                         Source: CEA, IMaCS Research

Recognizing the large potential of coal reserves in the country as an economic and readily available resource, a significant proportion of the future capacity additions is expected to be based on coal. Further, to reduce the environmental impact and to increase efficiency, the strategies proposed by the power ministry include introduction of large-sized units (660-800 MW) employing the super-critical technology. The source-wise capacity addition as envisaged under Eleventh Plan period is as given below:

Additional generation capacity would require commensurate investments in transmission infrastructure as well. Huge transmission capacity enhancement is required under Phase-III of National Grid Programme, which targets an inter-regional exchange capacity of 37,700 MW by 2012. With rapid industrialization and growing power requirements, many states have decided to set up high-capacity intra-state power transmission systems. PPP model is being adopted by many utilities to attract private investment in transmission sector. The future capacity addition plan envisaged is as given in the table below:

Projected Transmission Line Length (Ckm)

 

Sector

11thPlan

12thPlan

765 kV

5,428

8,000

500 kV HVDC

5,206

4,500

400 kV

49,278

51,000

220 kV

35,371

50,000

Total

95,283

113,500

Source: CEA,IMaCSResearch

Mandate for the Eleventh-Five Year Plan

Considering the continuing gap between the demand and indigenous production of crude oil and natural gas and low crude oil reserves, national oil companies and private companies are being encouraged to venture abroad. The various strategic options in this regard include focus on ventures with producing fields for the short term, equity participation as a part of reserves portfolio management, emphasis on exploration acreages for the short to medium term and promoting upstream sector services for the long term.

Planned Petroleum and Natural Gas Demand-Supply

 

      Ninth Five-Year

Plan (Actual)

Tenth Five-Year Plan (Actual) Eleventh Five-Year Plan (P)
Terminal year demand of petroleum products (Million tonnes) 100.43 119.85 141.79
Reserve accretion (MTOE) 795.13 1,652.92 2,129.44
Crude oil production (Million tonnes) 162.99 166.56 206.76
Natural gas production (bcm) 140.92 158.86 287.31

Net Imports –Terminal Year

Crude oil - 111.50
Petroleum products - -15.77
Refining capacity (Million tonnes) 118.37 148.97 240.96

Source: Planning Commission; P-Projected

At the beginning of the Eleventh Five-Year Plan period (2007-2012), the Planning Commission had projected a demand for gas of 279.43 million metric standard cubic meters per day (mmscmd) in the terminal year of the period, compared to 179.17 mmscmd in the first year of the Plan. The corresponding projection for increase in gas production was 63.23 bcm compared to 33.78 bcm.

Gas Production –Eleventh Five-Year Plan Projection (bcm)

2006-07

2007-08 2008-09 2009-10 2010-11 2011-12
ONGC - 22.10 22.53 22.77 22.99 22.00
OIL - 3.13 3.21 3.25 3.28 3.56
Private/JV - 8.55 22.55 29.41 28.77 37.61
Total 31.55 33.78 48.29 55.43 55.03 63.23

Source: Planning Commission

The projected demand for natural gas is the highest for the power sector, followed by the fertiliser, petrochemicals, city gas distribution and sponge iron and steel units. Any surplus gas after allocation to these industries would be available for sale to other units.

 

 

 

 

 

Projected Natural Gas Demand –Eleventh Plan Period (mmscmd)

 

2007-08

2008-09 2009-10 2010-11 2011-12
Power

generation79.7091.20102.70114.20126.57Fertiliser41.0242.8955.9076.2676.26Citygas12.0812.9313.8314.8015.83Industrial15.0016.0517.1718.3819.66Petrochemicals25.3727.1529.0531.0833.25Others*6.006.426.877.357.86Total179.17196.64225.52262.07279.43

Source: Report of the Working Group on Petroleum & Natural Gas Sector for the Eleventh Plan

Since the demand-supply projections for gas leave a significant unmet demand of 38.22 bcm, it is evident that gas imports would increase. According to Planning Commission estimates, by the end of 2011-12, India would import about 23.75 million tones of LNG. That could still leave an unmet demand of about 10-11 bcm.

LNG Supply –Eleventh Five-Year Plan Projection (Million tonnesper annum)

 

2006-07

2007-08 2008-09 2009-10 2010-11 2011-12
Dahej 5.00 5.00 5.00 7.50 10.00 10.00
Hazira 2.50 2.50 2.50 2.50 2.50 2.50
Dabhol - 1.20 2.10 5.00 5.00 5.00
Kochi - - - - 2.50 5.00
Mangalore - - - - - 1.25
Total 7.50 8.70 9.60 15.00 20.00 23.75

Source: Planning Commission

While the demand for crude oil has been projected by the Planning Commission to be around 207 million tonnesin 2011-12, the projected domestic oil production in that year is only 39-40 million tonnes. Going by the current trends in demand for oil and domestic production, the unmet demand could be higher than projected.

 

Crude Oil Production –Eleventh Five-Year Plan Projections (Million tonnes)

 

2006-07

2007-08 2008-09 2009-10 2010-11 2011-12
ONGC - 27.16 28.00 29.00 28.53 27.37
OIL - 3.50 3.55 3.73 3.91 4.30
Private/JV - 10.57 10.78 9.76 8.75 7.85
Total 33.98 41.23 42.33 42.49 41.19 39.51

Source: Planning Commission

  • Share/Bookmark

Submit a Comment

Your email address will not be published. Required fields are marked *

*

You may use these HTML tags and attributes: <a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>